A January launch has a December deadline.
Count six weeks back from a launch on Monday 18 January and the plan starts on Monday 7 December. Keep counting and the build phase, with the shoot and the edit, falls between 21 December and 4 January. If your business closes for Christmas, those are the two weeks it's closed. England and Wales also have three bank holidays inside them: Christmas Day on Friday 25 December, the Boxing Day substitute on Monday 28 December, and New Year's Day on Friday 1 January.
So for a launch in the first half of January, the deadline arrives before the office party. You have to shoot and sign off the content before you leave, which for a team that shuts on the last Friday before Christmas means 18 December.
January also gets crowded. Veganuary and Dry January both run through the month, so if you sell food and drink, or anything pitched as a fresh start, your category launches into the same four weeks as you.
The dates for four launch Mondays, 11 January to 1 February
The T-minus plan from the last Vibe Check counts back from the date. You write the brief at six weeks out, shoot at four, publish the first run-up post at two, and have everything finished one week before. These are the dates for four Mondays in January and February.
| Launch date | Brief by | Shoot | First run-up post | All finished |
|---|---|---|---|---|
| Mon 11 Jan | Mon 30 Nov | Mon 14 Dec | Mon 28 Dec (bank holiday) | Mon 4 Jan |
| Mon 18 Jan | Mon 7 Dec | Mon 21 Dec | Mon 4 Jan | Mon 11 Jan |
| Mon 25 Jan | Mon 14 Dec | Mon 28 Dec (bank holiday) | Mon 11 Jan | Mon 18 Jan |
| Mon 1 Feb | Mon 21 Dec | Mon 4 Jan | Mon 18 Jan | Mon 25 Jan |
Any deadline that falls inside the break has to move, either back to Friday 18 December or forward to the first week back. Posts can still go out over the break, as long as someone schedules them before you leave.
Get the January date sheet
All four dates on one page, bank holidays marked, with a blank row for your own date.
You'll also get Vibe Check every other Thursday. Unsubscribe whenever.
Here are your dates.
Download the January date sheet (PDF)If you launch on 11 January, everything has to be finished before Christmas, because T-1 is 4 January, the first Monday back. Bring the shoot forward from 14 December to 9 December, so the week of 14 December is free for the edit. The first run-up posts go out over the holidays, so you schedule them by 18 December. The brief is due on 30 November, eleven days after this goes out.
If you launch on 18 January, the shoot date of 21 December falls in the first week of the break. Move the shoot to the week of 14 December. The edit then fits into the first week back, while the problem posts go out, because most of those need no footage from the shoot. The first run-up post goes out on 4 January, the day you're back, so schedule it by 18 December.
If you launch on 25 January, the shoot date is the Boxing Day substitute. You can shoot in the week of 14 December, which means bringing the brief forward to 30 November so the shot list exists in time. Or you can shoot on 4 January, sign off the edit by 11 January, and have everything finished by 18 January. The second option keeps December free and leaves one week for the edit.
If you launch on 1 February, the build stays clear of Christmas. The brief date of 21 December falls in the break, so brief by Friday 18 December. You shoot when everyone's back on 4 January, and the run-up starts on 18 January with nothing to schedule over the holidays.
What to settle before your brief date
Put the date at the top of the plan and write the claim: the one line a stranger would repeat about your launch. Write the shot list next, then book the shoot day straight away, because in December freelancers and your own team both lose days to parties and leave. Last, decide who loads the posts that go out over the break, and give them a deadline of 18 December.
If a full shoot won't fit before the break, a shot list still will. A founder with a phone and a window can shoot from a good list. For a launch on 18 January or later, the edit can happen in the first week back. If even that looks tight, move the date to 1 February and keep the build out of Christmas.
Send me your launch date at hello@vibeshiftstudio.com and I'll tell you which of these weeks you're already in.
Find your week
The January date sheet as a one-page PDF, with the four dates counted out and a blank row for yours.
You'll also get Vibe Check every other Thursday. Unsubscribe whenever.
Here are your dates.
Download the January date sheet (PDF)Tyler / Vibe Shift Studio · London